CTRC - The California Trolley and Railroad Corporation.
Preserving the historical heritage of railroading and trolleys in the Santa Clara Valley of California.

CTRC Calendar

CTRC meetings are open to members and non-members.  You are welcome even if you are not a member.

We usually have a short (30 minute) discussion of status of the various projects.

We meet at 10am at the SP2479 locomotive restoration site in the double wide trailer.

Date: First Saturday of each month.

Time: 10am

Location:
2479 Healy Avenue
San Jose, California

Sponsored Links

Login Form



Welcome to CTRC

ImageEstablished in 1982, CTRC, the California Trolley and Railroad Corporation, is a 501(c)(3) non-profit organization with a mission to preserve and reflect the rich legacy of rail transportation in the Santa Clara Valley for the educational and recreational benefit of current and future generations.

Among the numerous projects underway is the restoration of Southern Pacific steam locomotive 2479.  CTRC has restored for operation a number of historic trolley cars.

A major undertaking is the creation of the San Jose Steam Railroad Museum with the focal point becoming the former six stall Lenzen Roundhouse and turntable.

 
32nd Annual Volunteer Recognition BBQ

31st Annual Volunteer Recognition BBQ
Thursday, August 20, 2015
5:00 p.m. to 7:00 p.m.
San Jose History Park
1650 Senter Road, San Jose, CA

BBQ provided by Retired Santa Clara County Firefighters

Music by the Singing Conductors

This is a FREE event in appreciation of CTRC’s dedicated volunteers and guests (Please RSVP so we know how much food to have available!)

Please RSVP by 8/14/14 to Lynda Ramirez Jones via email at:
This e-mail address is being protected from spambots. You need JavaScript enabled to view it or 408-691-2794

 
2479 Update - March 28, 2015

John Ezovski

Jan 24

Machining of second piston is underway.  If no issues are encountered, work could be complete next Saturday.  It#39;s nice to have access to a huge vertical lathe.  It may be taking up a large amount of floor space in the trolly barn, but it has been a valuable asset that has allowed us to complete a number or repairs.

Repairs to 75% of the boxcar roof is now complete.  The unfortunately nice weather is allowing this project to move rapidly ahead.

Warm weather plus December rains have stimulated grass and weed growth at the locomotive restoration and 1215 display site.  Both areas have been mowed over the past week.

Arrangements have been made with Andy Anderson at Oakland Machine Works to pickup the new valve cage Monday morning.

Jan 31

Small crew but we divided up into three groups and made some things happen.

Work on the second piston continues.  Once all the grooves have been trued each piston will be set back onto the King to make each slot a standard width.  This will help in forming in rings.

The boxcar roof is also coming along.  Repairs to the roof should be complete by the end of February, sooner if this dry weather continues.

SP1215#39;s rods received some attention.  Rust was beginning to form on the rods.  Rust was brushed away and a coat of paint applied.

Feb 7

Rain kept most everyone away from the locomotive site, but most of the work was being performed at the trolley barn.

Today#39;s news is not all good.  A close inspection of the engineer#39;s side piston revealed a number of cracks in the material that forms the sides of the piston grooves.  In some cases these cracks radiate through to the opposite side.

We are pretty certain that these pistons are cast steel, thus welding is a possible solution.  Cracks will be ground out and then filled with weld.  The piston will then have to return to the King for machining.  Repairs to the piston will most likely begin after next Saturday#39;s session.

Machining of the ring groove shoulders in the fireman#39;s piston is complete but not to a standard dimension.  That dimension can not be determined until after the engineer#39;s side piston is repaired.

Progress is being made on the box car#39;s roof.  Another 40 inch section was completed this past week.  Only 120 inches of roof line remains to be repaired.  That work could be completed this coming week.

Feb 14

Both pistons have been moved back to the fairgrounds site.  One piston requires numerous weld repairs to the piston ring groove walls.

With rain and warm weather, weed growth is in high gear.  Weed elevation was reset.

Repairs to the box car roof are complete.  The roof still needs painting but the crew will shift over to the MoPac caboose.  Its roof is in need of a good cleaning and paint.

Feb 21

In addition to maintaining site appearance, two major tasks were started.

The process of grinding out the cracks in the ring groove walls of engineer#39;s side piston was started.  This is going to take some time as there are a lot of them.  Its interesting that these cracks are all located in approximately the same half of the circumference of the piston.

The locomotive#39;s main and side rods are beginning to show early signs of corrosion.  Its been decided to pull all of the rods, clean and apply a coat of paint.  Paint will provide a better seal.  This paint will have to be removed prior to operation which means the rods will have to be removed again.

Pad welding on another this area of the firebox outer sheet was completed.  This section is ready for grinding and measurements.

Feb 28

Today the crew rolled locomotive and tender to keep journals and bearings lubricated.

The right main rod was removed for cleaning and a coat of paint.

More grinding on cracks in the walls of the piston ring grooves.  Presently we are working on the wall with the deepest cracks.

News is not all good.  The starter on the Clark lift is in need of a new Bendix unit.  The gear in the unit has been destroyed.

Mar 14

The right main and side rods have been removed, cleaned and a coat of protective paint applied.  This Saturday the rods will be set back into place on the locomotive.

Prior to installation, rod bores and driver pins will need to be cleaned and new coat of grease applied.  Once rods are installed, locomotive will have to be repositioned to allow removal of the rods on the left side.  If time allows removal of these rods can begin.

All of today's work was very heavy!

The right side and main rods were installed on the locomotive.  These three rods received a thorough cleaning and two coats of white paint.  Paint is to serve as a corrosion preventative.  Installation of rods was real smooth with work completed by 10:30.

Left rod set requires the same attention.  In order to remove these rods, the locomotive had to be rolled to different position.  This allows for removal of the main rod from the cross head and removal of the pin that connects the rear side rod to the front side rod.

Things didn#39;t go as well as we would have liked, but all rods were eventually removed.  Rods are now in a location that will allow cleaning.

Mar 21

Equipment failure kind of put a cap on the day.

During the week the left rod set was cleaned and painted.  Today those rods were mounted on their drivers.  As we were attempting to position the locomotive to mount the main rod, a hydraulic hose failed on the forklift.  There was a nice display of fluid spray from the hose.  (The hose will be replaced early next week.) ; Fortunately my jeep with a winch was able to finish positioning the locomotive to connect the crosshead to the main rod.

It has been decided that the new valve bushing will be pressed into place.  There was a lot of concern regarding soaking the bushing in liquid nitrogen.  At near -300 degrees F, the bushing could be very brittle thus easily damaged.  We are also worried about safely handing a 70 pound part at -300 degrees F.  Frost bite would not be much fun.  Pressing (actually pulling) the bushing in place will be more work but in the end it will be easier.

Mar 28

Good size crew and a bunch of stuff completed.  Thanks to all that participated.

As usual with this time of year, grass has to be cut at least every other week.  Today was the day.  Site looks nice.

This past week, the damaged forklift starter was rebuilt.  Today the unit was installed.  Also a damaged hydraulic hose was replaced.

Most of today#39;s work involved preparing to install the new left front valve bushing.  The front and rear valve covers were removed.  To remove the rear cover, the steam distribution valve crosshead and radius rod had to be disconnected from the cover.  Fortunately the assembly could be suspended clear of the work area with ropes.  If this could not be done, a lot of disassembly would have been required.

A plate is now being drilled to mount on the back end of the cylinder.  This plate will be used to hold four pieces of all thread.  The all thread will pass through another plate that will be set in front of the valve bushing.  Nuts on the front end will be used to push the bushing into place.  This is the reverse process that was used to extract the damaged bushing and it was removed without further damage. 

The process of setting the bushing should take place next Saturday.  Hopefully by noon time the task will be complete.

 
Status - January 19, 2015

John Ezovski

2014 ended with off with work continuing on both the piston and boxcar.

Another 40 inches of box car roof has been repaired.  By trial and error, a process has been developed which is yielding good results.  It will be late spring before the entire roof is repaired.  The filler, Evercoat, is rather nice to work with.  I have located another online source offering the material at a slightly lower cost.  It looks like at least two more gallons of material will be required.

Machining of the piston is a completely different story.  There have been issues with every step.  The tool holder has finally been finished.  The issue now is mounting the piston on the King.  Maybe next week the mounting issue will be resolved.

2015

2015 started off with a productive work session.

The first cut was taken in one shoulder of a piston ring.  There are a total of six shoulders in each piston requiring work.  Each step is a learning process.

Some pad welding was completed on the roof sheet of the firebox.  This area is getting close to meeting minimum thickness requirements.

80 more inches of box car roof has been repaired.  Repair of another 40 inch segment has begun.  A second gallon of filler material has been ordered and should be available mid week.  A long way to go before roof repairs are complete.

Thanks to John Zielinski for maintaining our various gasoline powered machines.  Without his help, this equipment would be neglected.

Organization of the peg board in the main container appears to be complete. Lots of work has been done here.

OSH Boxcar Doors

The park side door is beginning to move more freely.  Until recently it would take two people or one person with a crow bar to get the door open or closed.

Unless there are two or three people with some heavy tools, do not attempt to open the street side door.  The door is now securely closed with its wedge hammered into place.  From what I could see, neither of the door's wheels is making contact with the associated track.  This door is going to need some work if it is to be used in the future.

Pistons

Machining of the piston ring slots is on going.  As with most machining tasks, nearly all of the effort is in the setup.  A number of frustrating hours has been spent getting two of the three ring slots in one piston cleaned up.  In order to clean up the third slot, the piston had to be inverted which requires a complete new setup.  With some luck, the third slot could be finished next week.  This image is of the surface of the piston being machined flat prior to inverting the piston.

Repairs to the boxcar's roof are moving along.  Yesterday, repairs to the last two roof sections on the park side of the car were completed.  All that remains is to apply a protective coat of paint. This coming week, the work platform will be moved to the Senter Road side of the car so that repairs can begin on that side.  There is two to three more months of roof work remaining.

 
Status - June 10, 2014

John Ezovski

Vandalism on SP1215

Someone felt they had to gain access to the 1215's cab by kicking out the fireman's front window. Plastic window was destroyed.  Window frame was not damaged.  Repairs will cost about $20.00.

OSH Boxcar

Another big step towards getting OSH boxcar back on its trucks: Today, Larry, Denis and I started to wire brushed the ends of the car in preparation of applying paint.  Cleaning of the end of the car facing south is complete and ready for next step.  End of car facing north is about 2/3rds done.  I hope to have more of this work done tomorrow.

The next step in the process is to weld repair some of the rusted out areas on the ends of the car.  Patches need to be applied before painting.

2479 Site

In addition to the many cats, a family of foxes has taken up residence.

This morning I saw at least five animals living around the south-east pile of material.  Two may have been parents with three kits.  One of the kits is not very shy.  It walked up to within six feet of where I was standing.  I did not want to scare the animal but on the other hand I did not want it to become unafraid of a human.  There are to many mean people out there.  Image below is of the animal coming slowly towards me.

 
Status Update

Week ending May 3rd

It's been a busy week with again some good news and not so good.

The casting for the new steam distribution valve bushing was received earlier in the week.  John Ezovski successfully delivered one valve bushing casting to Andy Monday May 5th morning.  The HUGE machines in his shop are amazing.

Last weekend we failed at pressing a piston off its rod.  Our leaky press has a capacity of about 30 or so tons.  Bob Schneider contacted his contact at the VTA Light Rail Facility.  We were invited to bring a piston to their shops yesterday for observation.  The shop crew was excited to get on this thing with VTA's 300 ton wheel press.  The piston was mounted and the pressure brought up.  At 200 tons nothing happened.

At 250 tons more of the same, nothing! (and to think we were hoping to free it with our 'little 30 tonner').  At 300 tons, things were looking pretty grim.  After a few moments at 300 tons a rather loud bang occurred and things separated.  The piston and rod were two separate items.

Here is where the not so good news comes.  A crack developed in the nut end of the rod.  A rather significant disappointment.  Some better news, we believe a repair is within our capability.  Today the crack was ground out and is ready for welding. 

In the coming weeks, the rod's old threads will be cut away.  End of the rod will be built up with weld and new threads cut.  These repairs may not be completed until July as our mechanical adviser/journeyman machinist will be out of town for a number of weeks.

Earlier in the week, the fence along Healey Ave. was cut.  This section was repaired.  Improvements were made on two other areas that had been repaired some time back.

The leaky hydraulic press is receiving some attention.  A number of leaks are being corrected.  Improvements to the press are being studied.

As usual for this time of year, grass was again cut, weeds were killed, leaves were racked, fences repaired, etc.

Week ending April 26th

The cab roof tongue & groove boards have been cut to the proper sizes and only the creation of the tongue and grooves remain.

Other cab work completed:

  • Cleaned and primed all metal surfaces.
  • Cleaned and primed all attaching components presently stored in a shed container.
  • Created link extensions to allow the roof vent to be completely extended.
  • Created engineering drawings of all cab wood components.
  • Unwanted holes filled.
  • Rusted rain gutters repaired.

Week ending April 19th

Over the past three weeks base material, ballast, ties, and rails have been laid in front of the 1215 locomotive located at History San Jose.  This is so we can eventually move the 1215 locomotive forward enough to insert the Orchard Supply Hardware box car between it and the caboose.  We will then have a real train.

 
Lost Postings of 2013

Several items fell through the cracks:

June 29, 2013

100 degree temps only slowed us down a little!

Machining of the bushing for the left rear side rod number 3 driver was completed during the week.  This morning it was pressed into place.  Measurements were then taken to determine if the buffering ring was of the proper width.  Unfortunately the bushing was to long.

The buffering ring prevents the bushing from being pressed out of position in the rod/bushing come in contact with the washer which is between the rod and nut.  If the bushing moves it will wear inside the rod and eventually become sloppy in the rod.  The buffering ring is pressed on the end of the bushing.  If fit is proper, the end of the bushing should be slightly lower inside the ring.

With the bushing being to long, it was pressed out and trimmed.  Bushing was then pressed back into the rod.  Buffering ring pressed into place.  Rod was then moved to the locomotive.

There were no issues getting number 3 pin to accept the rod.  Problems came about with alignment of the front end of the rear rod to the knuckle at the rear of the front side rod.  Number 3 driver was needed to come forward about one eighty of inch.

A 20 ton bottle jack was set between the locomotive frame and a large spoke.  Heavy gear oil was brushed between the rail and wheel.  Jack was then used to rotate the wheel a very small amount.  Surprisingly the wheel did rotate rather easily considering the weight the wheel bears!

There was a bit of "house" keeping performed.  Securing of the galvanized steel sheets that were hung on the front shop doors was completed.  This coming week a coat of primer may be applied.  The back wall of the outside shop will now be covered with the remaining galvanized material. Presently a large plastic tarp covers this area.  This tarp is about to fail and would be expensive to replace.

July 27, 2013

Movement forward on several fronts.

The bushing for the right main rod is coming along.  The inside and outside diameters are complete.  Bushing now must be cut on band saw, and finished.  Locating and drill of the many grease holes will follow.

Cleaning of the main rods is complete.  The last side was finished today.

One set of caboose steps was sanded and coat of paint applied.

During this past week, a good deal of time was allocated to the locomotive's steam dome cover.  The present cover is to thin.  It was noted on RYPN that the TVRR had purchased a new cover for their 4501.  Contact was made with TVRR.  They used the vendor that was being considered to form 2479's new cover.  Cost was in the vicinity of $500.  This is good news.  A quote request for a new cover for 2479 will be submitted this coming week.

August 10, 2013

Machining of the last two bushings continues.  21 grease holes have been drilled and chamfered in the bushing for the right main.  Chamfering of the holes on the inner surface and cutting a radius on the inside edge remain.

Machining of the left main bushing is about 50% complete.  The inner and outer diameters are complete.  The end of the future bushing that was clamped in the jaws of the Le Blond chuck was cut on a band saw.  A bunch of work remains.

Repairs to the cab are ongoing.  Welding in a section of the engineer's rain gutter continues. Some good head way was made today.

Hyster forklift has had problems with the right front tire loosing pressure.  Inner tube was patched twice but leak continues.  New inner tube was installed today.  This little forklift is handy when heavy items have to be moved into the outside shop.

Improvements to the outside shop continue.

August 17, 2013

This morning machining of the right main rod bushing was completed and the main rod installed.  Installation went rather smooth.  The rod will have to be removed once the pistons are installed to check limits of piston travel.  It was felt that bushing and rod surfaces are better protected by storing them on the locomotive.

Bushing for L2 main rod driver pin is about 60% complete.  Locating, drilling and chamfering of grease holes is next.

Art has machined two new grease fittings for the driver pins.  At the moment CTRC does not own an Alemite stick grease gun.  It also appears that there are no vendors for the large button head fittings previously used by SP.  Art has machined an adaptor with a 1/2" button head grease fitting.  We do have an pneumatic grease gun capable of pushing grease threw the pin and bushing passages.  Two of these adapters were installed and tested.  Looks like rods and pins can now be lubricated during the remainder of the restoration.  Art is going to machine adapters for the remaining four pins.

Problems today with our portable battery charger.  Some tinkering and unit was again serviceable.

We are studying a different way of attempting to roll the locomotive.  There is concern that the present method of forklifts and chains is going to cause serious damage to one or both forklifts.

During the week material for a new steam dome cover was placed on order.  Total cost for this cover is $417.00.  Cover will be near identical to the present cover but heavier in all of the necessary places.  Object should arrive late September.

August 24, 2013

Machining of the last bushing, L2 main rod, is complete! Today we located, drilled and chamfered the 21 grease holes.  With this work out of the way, the bushing was again test fit.  Next Saturday morning the left main rod will be mounted.  For those interested in observing, work should being about 9:30 AM.

Another big "Thank You!" to Karen and Jerry Lane for the grant that allowed CTRC to move a big step forward in the restoration of X-SP-2479.

Adaptors for 1/2 button head grease fittings have been machined.  This will allow grease to be injected into the pins and rods during the remaining restoration period.  Keeping grease in the rods will prevent corrosion from forming in the bottom of the rods.

August 31, 2013

Today the left main rod was returned to the locomotive.  Installation of the rod and main pin bushing went rather well.  Several hours were spent cleaning and repairing the threads in the crosshead pin for the grease adapter.

In the above image the cross head pin is sitting on a tie adjacent to the rear wheel of the engine truck.

Repairs to the rain gutter on the engineer's side of the cab are complete.  A section of the gutter was cutter away and a new section welded into place.

September 7, 2013

Day was spent forcing grease into a couple of rod pins.  Finally were successful getting grease into both cross head/main rods and the main rod bushing on left side.  I'm not sure about grease making its way back to the main pin's side rod bushing on the left side.

Believe most of the work on the engineer's side rain gutter is complete.

September 28, 2013

Small crew today.

We were unable to verify that grease was flowing threw the number 2 left driver pin to the bushing for the front rod.  It was deemed necessary to pull the left main and front side rod.  The grease passages in the left main pin were cleaned and grease flow was verified.  The rods were then installed.  Process only required 3.5 hours.

The new steam dome cover is suppose to ship Monday from Fort Worth, TX.  I would expect it to arrive late in the week.

October 1, 2013

New cover arrived this morning.  Initial measurements are excellent.

October 5, 2013

Several significant tasks under way.

Several of the machining steps on the new steam dome cover have been completed.  The gasket side of the cover was machined flat earlier in the week.  Today the top side of the flange was machined flat and a center hole was drilled and tapped.  The preceding steps were completed on the barn's Leblond lathe.  (We could not have completed a good number of tasks without that machine!) The cover will now be moved to the restoration site, where 24 one inch holes will be drilled.

Our welder has returned from an extended "vacation" in Pennsylvania.  Welding upon the firebox wrapper sheet on the fireman's side has again begun.  A good number of pounds of welding rod is going to be required in building up thin areas.

More of the cab sides have been wire brushed and primer applied.

October 19, 2013

Small but productive crew.

Firebox wrapper sheet pad welding- Light grinding and sanding was performed on the welded area on the fireman's side of the firebox wrapper sheet.  Ultra sonic measurements are much improved but a second pass is going to be required.  That process started today.  Unfortunately the welder ran out of the needed rod with about 1/3 of the work complete.

Steam dome cover- After 8 attempts and adjustment in hole location, the new steam dome cover finally accept the dome's studs.  It appears that at least 12 studs will have to be replaced to provide proper length.

Cab- The cab's side vents were removed and hinges cleaned.  Vents now move with ease.

Winterizing locomotive- Now that rod bushings are in place, new plastic tarps were acquired and set in place to provide protection from up coming seasonal rains.

Thanks to all that participated.

November 2, 2013

As in the past, there is progress.  Over the past two weeks, 22 of the 24 steam dome studs were extracted from the dome.  This was necessitated due to the thickness of the new cover.  Studs were removed by welding a nut on to the stud.  An large air impact wrench was then used to unscrew the stud.

Machining of new studs is well underway.  Three of the new studs are already in the dome.  If all goes well, all studs should be back in the dome by close of business next Saturday.

Pad welding on a large area of the firebox continues.  The area that is being built up is about 12 inches by 5 inches.  Two passes have been completed.  The area requires grinding and ultra sonic after which ultra sonic measurements can be taken.  A third weld pass my be required in a smaller area.

Cleanup upon the exterior of the cab continues.  If weather holds, a primer coat will be applied to the exterior next Saturday.

November 9, 2013

Several members that have not been available fir some time joined today's work crew and helped make this a extremely productive session.

Today the new steam dome cover was set into place.  This is a significant mile stone.  In September of 2005 (yes, eight years one month past) calculations based upon ultra sonic measurements revealed the old cover to thin.  Regardless of how the calculations were manipulated, the results were always the same, cover not serviceable at 210 PSI.

Machining on cover was completed several weeks ago, but the thicker cover required replacement of 22 of 24 dome studs.  Material for new studs was on hand.  Longer studs were machined.  Today those studs were set tight.  The new cover slipped into place after a couple of small "adjustments" were performed.

Every 3 or 4 months the locomotive and tender are rolled to keep journals lubricated.  In the past, two forklifts were employed.  The Clark forklift although large is not suitable for this task.  Its not geared low enough.  Over the years of CTRC service, several components in the drive line have failed.  Continued use this machine in this manner eventually lead to another costly if not catastrophic failure.

Today we experimented using a jeep winch and pulleys to pull the locomotive.  The Wiggins lift was required to assist climbing a rail joint other wise the move went well.  There are a couple of issues to resolve.  It now appears that the only use of the Clark during future moves of the locomotive is as an anchor for the jeep.

The stairs that are used to access the locomotives cab area received some much needed help.  A new brace was added and preparations were made to apply a new coat of paint.

The surfaces of the turntable and stand for the water tank were cleared of leaves from the pepper tree.  Request has been made to fairgrounds staff to have the tree pruned which may happen in the next week or two.

November 26, 2013

The OSH Box car that sat along Azuerais Ave.  for 50 plus years was moved today to San Jose's History Park.

In the coming weeks the display track that SP1215 and MoPac caboose sit upon will be lengthened and the boxcar set between the locomotive and caboose.

The move would not have gone as nice as it did without the help of Tom Anderson and Larry Murchison.  On Saturday, Tom helped preparing the car and getting cribbing materials pre-positioned.  Today, Larry helped positioning crib material to set the car body upon.

November 30, 2013

Measurements were taken of the inside diameter of the cylinder that holds the left front valve cage. This was needed to update the valve cage drawing.  Once an accurate drawing has been created, the drawing can be submitted to vendors for machining of a new cage.

Performed NDT on one of three of the locomotive's air reservoirs.  News is not good.  A deep gouge and waste area was found on visual inspection.  The area was polished to form a flat spot for the transceiver of the Ultra Sonic Thickness gauge.  Measured thickness was .177.  Calculations call out a minimum thickness of .223 for a 110 PSI air system.  By Part 230 rule, air reservoirs can not be repaired.  This tank is not fit for service.

Over the coming weeks the remaining tanks will be inspected.

December 7, 2013

Not much accomplished today.  Lower temperature and moderate wind kept all hands close to heaters.

Some time was spent examining the second of three air tanks.  Again news is not good. A waste area of substantial depth about size of a dime was located on the largest tank, 90" length.  Two tanks now not serviceable.

Drawings will be constructed.  Once reviewed, drawings will be sent off to ASME shops to obtain quotes.

December 15, 2013

A bit of progress yesterday.

Cab - Furring strips along the front and rear of the cab roof that were cut out and installed years ago by the trolley group were installed with more appropriate hardware.  Repairs to the last segment of damaged fireman's rain gutter was started.

Cab will soon be ready for wood liner.

Left Front Valve Cage - Very accurate measurements were taken of the inside surface in the left front valve's cylinder.  These numbers are needed to complete a drawing for the new valve cage.  Several other small issues remain with this drawing.  Drawing should be ready for quotes in early January.

Air Reservoirs - Third air tank was removed from the locomotive to enable inspection.  A generic drawing has been started to be used to obtain quotes.  Hopefully all work will be complete and ready for quotes by the end of January.

Boiler - Grinding and polishing of an area on the fireman's side of the fire box that has seen several layers of pad welding applied.  This area is about 5 inches by 24 inches.  Ultra sonic (UT) measurements were taken.  Welded area now meets required minimum thickness.  There is still a significant area to be welded along top and one side.  Fortunately there are no restrictions on the size of an area that can be pad welded in a stayed area, otherwise this would have been a very expensive repair.  There are several other areas requiring pad welding.  These areas are smaller then the section presently under repair.

A UT measurement was taken in each square in the above image and is recorded.  A bit more grinding and polishing is needed to complete the work.

 
Annual Board Meeting and BBQ - August 15, 2013

Rod Diridon

This 30th year CTRC Annual Board meeting and BBQ promise to be quite exciting.  We hope to be able to announce another major successes and hope even more that you might join us for these special events.

The Board meeting is open to the public and begins at 3:00 PM in the Pacific Hotel conference room at History San Jose at Kelly Park.

The BBQ begins at 5:00 PM, Thursday August 15 and is free to CTRC supporters and a guest ... but please RSVP to Lynda (408 924 7561 or Lynda Ramirez Jones - This e-mail address is being protected from spambots. You need JavaScript enabled to view it ) to help with the meal count.

For the 30th time Dennis DeMelloPine and the retired County Firefighters will provide the food and the Singing Conductors will again entertain.

Senator Jim Beall, new County Supervisor Cindy Chavez, and Vice Mayor Madison Nguyen will welcome you and one of our historic trolleys will be operating...a special treat for youngsters of all ages.

In the last 30 years CTRC has raised over $3 million and parlayed that into over $20 million in physical assets for the Valley including nine historic trolly's restored and construction of a mile of electrified trolley tracks and the CTRC trolley barn at History San Jose.  We're nearing the completion of the rebuilding of the County's massive steam locomotive #2479 at the County Fairgrounds and have acquired three more historic locomotives and several historic rail cars in preparation for the soon-to-be-built steam railroad museum.

All of those assets have been built, maintained, and operated at no cost (with the exception of sincerely appreciated County Historic Hermitage Commission competitive grants) to the taxpayers by the phenomenal CTRC volunteers and donors who we honor on 8/15. Thanks to each of your for your continuing strong support.  We look forward to being with you soon.

 
Museum Development - July 2013

On July 9th, 2013 CTRC members Rod Diridon, Marv Bamberg, and Larry Murchison met with Jamie L. Matthews, mayor of the City of Santa Clara and Julio J. Fuentes, the city manager to discuss a possible location for a CTRC railroad museum.  The location discussed is the triangular area (east of the tracks) at the very northern end of Lafayette at the corner of Yerba Buena Way.

While no decision was reached concerning this property a request was made by CTRC to also look for some other location that might offer better acreage and railroad access.  Jamie and Julio gladly accepted this challenge and will be working with Rod and Marv.

The accompanying pictures show that Jamie has a railroad background.

Top: Jamie's grandfather, great grandfather, and great, great grandfather on the Alameda.

Bottom: Jamie's grandfather as conductor of original trolley Franklin St.


View Larger Map
 
SP2479 Saturday, June 22

John Ezovski

Lots accomplished this week.

Machining of the bushing for the main pin of left front side rod (L2) completed. The rod was installed on the front pin. Attempt at pushing the L2 bushing into the rod and on the pin failed. It looks as if the number 2 drive must be moved forward a very small amount. Slipping the driver forward was left for next week.

The blank that will become the bushing for the left rear side rod number 3 driver (L3) was set in the trolley barn's Le Blond lathe. This coming week machining of this bushing will begin.

The feed water heater and air pump were inspected. These objects were placed inside a small garden shed several years ago. Both units are in good shape with no evidence of corrosion. Polished piston rods were coated in oil and crates secured in the shed.

The two 6 foot long 8 foot tall doors at the back of the outside shop were cleaned, primed and painted. These doors were covered with the remnants of a garden shed about two years ago. These pieces of sheet steel were a number of different paint colors which did not look very nice. From the Old Tully Road, these doors now look pretty good.

There are two similar doors are on the opposite end of the outside shop. Until recently these doors were covered with plastic tarps. Tarps were removed due to their deterioration. A stack of various lengths of used galvanized corrugated sheet steel has been obtained at a good price (free). The front doors to the outside shop are now covered with this used material. In the future, the doors will also be painted.

Thanks to all that participated.

June 26 Update

Saturday the crew was not able to insert L2's bushing onto its pin/into the rod. It was thought the wheel was possibly out of position.

This morning I thought I would get a head start on the weekend by taking a measurements between the L2 pin and rod. With this data it could be determined which direction and how far the wheel would have to be moved.

To help make the task easier I machined a piece of 7/8" round stock down to a dimension .002" smaller than the clearance between the wheel's pin and rod. A bottle jack was used to raise the rod off the wheel's pin. The machined piece was inserted at the top of the pin and the rod lowered on to the machined piece. The rod was then raised a very small amount to allow the machined piece to be removed. Measurements were then taken at the cardinal points using a small spring caliper. There were no significant differences between the four points.

At this point, I tried to insert the bushing onto the pin and into the rod.

 
SP2479 June 15

John Ezovski

The day began by installing the right front side rod. Expectation was not high at being successful. There was no way to predict the position of driver 1 and 2 to each other. The drivers were install with the old bushings in place. Since these old bushings were sloppy on all pins, it was thought that pin position to each other may be slightly off. The rod was pushed into place on the front pin. When it came time to push the main pin's floating bushing into place, all were rather surprised when the bushing slid into place with minimal effort!

Next the R3 bushing was pressed into the rod and the rod installed. The only issue to be resolved is alignment of the knuckle pin's nut to the locking rod grooves, otherwise work on the right side rod set is complete.

Machining of L2 bushing for the left front side rod will begin this week.

 
<< Start < Prev 1 2 3 4 5 6 7 8 9 10 Next > End >>

Page 1 of 11

Sponsored Links