Steam Gauges for the 1215

Photos of the steam gauges for the 1215 have been uploaded into the photo gallery.

Here's the description from Hugh Crawford:

ImageThese gauges, as you see, are "double spring" meaning there are 2 Bourdon tubes linked together mechanically.  These are more accurate gauges.
 
Here's what's been done so far:
 
Disassemble and clean - they were packed full of mud dauber mud.
 
Bead blast the cases and paint with high heat engine enamel.
 
Both linkages with hair springs were ultrasonically cleaned.  One spring was straightened and reattached to the shaft and the shaft was straightened. - This was done by a Swiss trained jeweler.
 
Strip and polish the brass rings to secure the glass.
 
Reassembly
 
Ordered tempered glass
 
ImageNeed to do:
 
Paint faces, install glass and needles, dead weight test through their operating range.
 
Any comments are welcome.  I'm learning on this one.
 
Thanks to Al Paolo at CSRM for his advise and help straightening the dented face.  Leonard for his gauge restoration and face painting advise. 
 
< Prev   Next >

Latest News

Today (September 3, 2008) Bay City Boiler completed the welding of the unstayed areas on the SP2479's boiler. The thickness of each welded area was verified with the electronic thickness guage. All that remains to this task is the filling of forms with the Federal RR Administration within 30 ...
Caboose and Tender Move On Saturday August 30, John Zielinski led a crew (listed below) to complete the move of the caboose and tender. The cars are now nicely positioned along side the two passenger cars.  All that remains is cleanup of some material laying about the grounds.  To...
For years, CTRC has searched for a smaller steam locomotive.  While a second Southern Pacific locomotive was desired and ultimately fulfilled with the acquisition of 0-6-0 switch engine 1215, an even smaller steam locomotive has been sought as a demonstration exhibit and/or possible use on ...
1899 Santa Fe Railroad Steam Locomotive “Little Buttercup” Santa Fe 0-4-0 #5 Little Buttercup began life in 1899 as an 0-4-0T built by the Baldwin Locomotive Works as Santa Fe Terminal #1, for operation on the Santa Fe trackage in San Francisco’s China Basin.  Built ...
Date: March 25, 2008 Subject: Colorful 109 year old steam locomotive added to San Jose Railroad Museum’s growing roster. From: Rod Diridon, Chairman/President California Trolley and Railroad Corporation Contact: ...

CTRC Calendar

CTRC meetings are open to members and non-members.  You are welcome even if you are not a member.

We usually have a short (30 minute) discussion of status of the various projects followed by a program.

We meet inside the Santa Clara railroad station itself (you may have to slide one of the sliding doors open to find us.)  In the winter be sure to bring a coat - it can be a bit cool inside the station.

Date: First Monday of each month.

Time: 7pm

Location:
   Santa Clara Railroad Station
   1005 Railroad Avenue
   Santa Clara, California

Click here for map

Upcoming Meetings:

Regular Meetings
  2008
   October 6
   November 3
   December 1
  2009
   January 5
   February 2
   March 2
   April 6
   May 4
   June 1
   July 6
   August 3
   September 7
   October 5
   November 2
   December 7

Sponsored Links

Submissions

Please send news and other materials by email to karl at cavebear.com.

Syndication

Login Form






Lost Password?