From John Ezovski
Lack of electrical power did not inhibit today's progress.
The Clark forklift was in need of maintenance.
A number of items were
addressed and the forklift made available for service.
Positions in the designated area for the locomotive, containers, double
wide trailer and outdoor shop were identified and marked.
Machining of the lead truck bowl was completed at the trolley barn and
the part returned to the fairgrounds.
The only work that remains to complete
the lead truck is machining of two rings that sit inside the lead truck bowl.
During this past week, the weekday crew continued to consolidate rail and
ties, that were located at the east end of the big rail and tie stack, to the
new area.
This task continued today. Hopefully cleanup of this section
will be completed by Wednesday of this coming week.
|
|