Today's major task was the installation of the three remaining wedges and pedestals binders.  This task consumed most of the day.

An issue remains with the right wedge for number three driver.  It was decided that pulling the locomotive back a small distance might help correct the problem.  For the first time since December 1990, the locomotive rolled easily upon its own wheels (with a forklift providing power).

While the group struggled with wedges and binders other members continued to relocate materials to the new area.  No additional material can be relocated until new site preparations are complete.

 