CTRC - The California Trolley and Railroad Corporation.
Preserving the historical heritage of railroading and trolleys in the Santa Clara Valley of California.

CTRC Calendar

CTRC meetings are open to members and non-members.  You are welcome even if you are not a member.

We usually have a short (30 minute) discussion of status of the various projects.

We meet at 10am at the SP2479 locomotive restoration site in the double wide trailer.

Date: First Saturday of each month.

Time: 10am

Location:
2479 Healy Avenue
San Jose, California

Upcoming Meetings:

Regular Meetings

  2012
   August 4
   September 1
   October 6
   November 3
   December 1

  2013
   January 5
   February 2
   March 2
   April 6
   May 4
   June 1
   July 6
   August 3
   September 7
   October 5
   November 2
   December 7

Sponsored Links

Login Form



SP2479 Status - Sept 29, 2012

John Ezovski

Today's crew was small but a bunch of work was completed.

Prior to departing on vacation our master mechanic machined two grease fitting adaptors for the frame which allow lubrication to the reverse link pins.  There were issues getting grease to flow around the left side frame's inside reverse link bushing but they were overcome.

Today the reverse link and radius rod were installed.  None of the issues that were experienced on the right side were encounter.

Cleaning and painting of running boards continues and is near completion.  The upper surface on the right side including the engineer's platform are now complete.  The fireman's platform has been cleaned and primed.  The "well" area between the engineer and fireman have been wire brushed also wire brushed was the apron between the locomotive and tender.

The piece of bronze needed for a new bushing for the engineer's side of the reverse rod has been received.

 
SP2479/SP1215 - Sept 1, 2012

John Ezovski

SP2479

The past couple of work sessions the crew struggled with assembling the right side reverse link, radius rod, and combination lever.

The combination lever pin would not seat in the valve cross head.  After three plus hours of filing and polishing with emery paper, the pin was seated and secured with tapered pins.

Assembly of reverse link, reverse link block, cheeks and radius rod were next.  Bolts that hold secure the cheeks and capture the reverse link are fitted.  Each hole and bolt was marked by SP.  The first bolt did not fit its assigned hole.  As the afternoon wore on, the task was terminated.  Measurements of the bolts and holes were taken before returning components to storage.  It was noted at this time that bolts did not match assigned holes.  Bolts were then matched to holes.

Yesterday the reverse link assembly was bolted into place.  Assembly went off with no issues.  Securing the radius rod to the cross head did present some problems.  The pin which retains the radius rod to the cross head would not fully seat.  A small amount of filing on the pin resolved the issue. (See photo.)

Tramming of the cross head for the left steam valve is now under way.  Yesterday a wire was centered in the bore of the cylinder and measurements taken.

Cleaning and painting of running boards continues.  Running boards on the left side are complete. Right side is in work.

SP1215

Locomotive at History Park has begun to show affects of weather.  Some polishing of rods and a coat of clear lacquer has been applied.  Windows are in the process of being repainted.

 
29th Annual Volunteer Recognition BBQ - Thursday, August 16, 2012

29th Annual Volunteer Recognition BBQ
Thursday, August 16, 2012
5:00 p.m. to 7:00 p.m.
San Jose History Park
1650 Senter Road, San Jose, CA

Beverages provided by Bottomley Distributing Company

BBQ provided by the Santa Clara County Firefighters

Music by the Singing Conductors

This is a FREE event in appreciation of CTRC’s dedicated volunteers and guests (Please RSVP so we know how much food to have available!)

Event Title Sponsor: Wells Fargo Bank

Sponsors: Dan Caputo Company, Cupertino Electric, Hatch Mott MacDonald, Hensel Phelps Construction, HNTB, KLIV/KARA Radio, and Anonymous Donor

Please RSVP by 8/9/12 to Lynda Ramirez Jones via email at:
This e-mail address is being protected from spambots. You need JavaScript enabled to view it or 408-924-7560

 
SP 2479 Saturday July 28, 2012

John Ezovski

Paint has been applied to all remaining areas of boiler.  Boiler courses 1, 2, 3, and firebox from running board up over roof sheet to opposite running board now have a fresh coat of black.

Weld build up the second combination lever pin hole in cross head for left steam distribution valve.

Inspect reverse shaft bearings.  Found fireman’s side bearing okay.  Engineer’s side bearing exhibited severe wear thus must be replaced.

Complete improvements to power cables to Bridgeport mill and Hardinge lathe.

 
SP2470 Status

John Ezovski

June 30

Traming of the cross head for the right steam distribution valve is nearly complete.  Adjusting the cross heads position with shims has consumed two worker's time over the past two weeks.  It now appears that the cross head is in a good position to accept the valve's rod.

Two tasks remain before the valve can be inserted into the cylinder.  The two bolts that attach the right upper and lower guides must be replaced.  These will be machined in the coming week.  A grease fitting and path need to be added to the outside lower guide.  Once this work is complete, the task will be repeated on the left side.

Upper surfaces of the locomotive's boiler have begun to show affects of weather.  Flexible staybolt caps and sleeves show the most weathering.  To prevent damage, most of the boiler will be wire wheeled, primed and painted.  This task is well under way.  Above the running boards on the fireman's side, barrels 1 and 2 have been thoroughly wire wheeled and primed.  The backhead and the firebox wrapper sheet above the running boards on the engineer's side has seen the same service.

July 14

Wire brushing and application of primer to boiler continues.  Except for two small areas primer has now been applied to the boiler and firebox from the running boards on one side, up over the top of the boiler to the running boards on the opposite side.

Traming of the cross head for the left steam distribution valve is on going.  Both holes in the cross head that holds the pin which connects the upper end of the combination lever are over size and out of round.  The upper and lower "bridges" were thin.  Decision was made to weld up both holes.  Today the first hole was built up.  During the coming week the welded area will be bored.

A wire was position in the middle of the left steam distribution cylinder.  Several measurements were taken.  Until the cross head is finished this process can not continue.

 
Aux Dome Cover - June 9, 2012

John Ezovski

Machining of new aux dome cover is complete.  Today the cover was hoisted into place to check for fit.  After a few "adjustments" cover slipped into its new home.  Next week the aux dome cover gasket will be annealed and cover set into position.

Shown is an image with safeties, valve and whistle in place.

 
SP2479 Update - Saturday, May 26, 2012

John Ezovski

Nice size crew today.

With the restoration site being in a highly visible area, appearance is important.  Today a group of workers trimmed trees of low branches passing threw the fence.  Removal of these branches also helps with site security.

Although the lawn tractor does not see heavy use, performing preventative maintenance on the machine is a necessity.  A number of items were addressed needed to help extend its life.

The locomotive's boiler is beginning to show weathering.  Wire wheeling and painting of the boiler has begun and will continue for many more weeks.

The real good news is the fourth and final hole in the center area of the new aux dome cover has been threaded!  The new cover was removed from the Le Blonde lathe and returned to the restoration site for remaining work.

All twenty studs needed to mount the new cover have been machined.  Five of the studs were set into place.

 
Status Update - May 6, 2012

John Ezovski

The majority of today's steam crew spent the day working at the trolley barn.  Two members worked at returning the barn's Clark forklift to a serviceable state . This machine has not run for several years.  The battery required extended charging and a multitude of ignition issues were repaired.  By days end, the forklift was running.

Progress has been made with the new aux dome cover.  Holes for the two safeties, valve and whistle were bored to an optimum diameter during the week.  Today the gasket seating surface was machined flat on the Le Blond lathe.

Next came the big test.  Could the lathe turn the heavy plate offset five inches from center without counter weights being attached?  The first of two safety holes was centered and the machine powered on.  There was no noticeable difference in rotational rate of the chuck Tapering and threading of the hole began.  By secure time, the first of four holes was complete.  A significant step forward.

At the locomotive restoration site, several other tasks were underway.  Components to provide tender water level to the cab crew were being manufactured.  Nice weather requires weekly grass and weed control.

 
SP2479 Aux Dome Update - April 28, 2012

John Ezovski

Threading of second hole in test plate was successfully completed.

A machining plan has been created for the aux dome blank.  Four holes to be threaded in blank were located. Boring of these holes will begin this week.

 
SP2479 Aux Dome Report

John Ezovski

April 7:

Progress has slowed. Upon receipt of the aux dome cover blank, it was decided to practice machining with a piece of scrap plate.  A suitable plate was prepared and a number of small holes bored.

Biggest concern is threading holes for the three inch safeties.  Finished holes will be approximately four inches in diameter with an 8 pitch thread.  CRTC's only machine capable of this work is the Leblond lathe located in the trolley barn.

This machine has not been used in a number of years.  It required cleanup and lubrication.  During this process several deficiencies were noted.  A piece of the taper attachment was missing and was constructed.  The biggest concern is wear in machine parts.  It was noted that there was a near half turn revolution of the crossfeed handle.  The lead screw was removed and inspect. Both the lead screw and nut are heavily worn.  The compound feed is also very loose.

Obviously destroying a four hundred dollar part is not on the task list.  Currnet condition of the lathe is a major concern but we are not ready to give up. Next Saturday the test plate will be mounted.  An attempt at boring and threading of the first large hole will begin.  Upon completion a look at direction will be taken.

April 21:

Weeks of cleaning, fixing and understanding the trolley barn's Leblond lathe has paid off!  Yesterday, 2479's master mechanic tapered and threaded a four inch hole in the test plate!  A cap was set into the hole to prove the work.  With the first hole complete, the test plate was repositioned.  This hole will also be tapered and threaded for added experience.

In image, note plate off-set from chuck center.  The lowest rotational speed of the chuck was being used.  This plate weighs less than half that of the new cover.  The task is looking much more do able on this lathe but there is still a question as to the lathe being able to turn the heavy part off center.

Saturday work crews continue to be very small.  The remainder of the crew has been working at site appearance.  Rain followed by sunny, warm temperatures have kicked grass and weed growth into high gear.  Keeping the storage areas clear of tall weeds is difficult and time consuming.

 
SP2479 - Sat. March 3, 2012

John Ezovski

The blank for the new aux dome cover was received during this past week.  The diameter of the piece is slightly less than 20 1/2".  And it is 2 inches thick.  In the attached image, a nut that is 7/8" tall was placed on top of the plate to give a sense of size.

Dealing with the blank for the new aux dome cover was the focus of this past Saturday's session.  Boring of holes in this cover for the safeties and other objects will present a significant challenge.

The safeties, whistle and vent valve were mounted on the old cover to verify clearances.  Holes for each of these objects may be relocated slightly.

Prior to cutting into a $400.00 piece of steel, we will experiment on a piece of scrap plate.  A one inch piece of material was located, cut and cleaned.

The trolley barn's big LeBlond lathe is the only CTRC machine capable of performing this work.  The lathe was examined for tooling.  It appears that there is a piece missing for the taper attachment but should be easy to fabricate.  Only if we are successful with the piece of scrap plate will work will begin on the blank, otherwise services of a machine shop will be necessary for the large holes.

 
<< Start < Prev 1 2 3 4 5 6 7 8 9 10 Next > End >>

Page 2 of 10

Sponsored Links