Home
2479 and 1215 Update - August 25, 2007
Image

Measurements of the locomotive frame continue with tram wires and wheel gig installed on the locomotive.

Image

Wire brushing and painting of the boiler continues around the firebox.

Ford forklift parts were organized and stacked on pallets.

The planning section will discuss the move of 1215.

 
2479 Update - July 7, 2007

From Jack Young

Tram wire adjustment on the locomotive continues.

Shoes and wedges were remeasured to double check size before final machining.

Prep work for sealing two rigid stays is in process.

Miscellaneous piping was wire brushed and cleaned.

The original boiler jacket is being laid out on the ground to determine location on the boiler so drawings can be made.

Ford fork lift is being drained of fluids.

Chain saw was cleaned and tested – This will be used to cut the cribbing for the locomotive.

 
2479 Progress Report - June 30, 2007

Completed weld repairs to locomotive's brake foundation.  Cleaning and painting of boiler continues.  Tram wires have been strung to allow further measurements with shoes and wedges in place.

Repairs to the Clark forklift are complete.  Several minor mechanical issues have been addressed.  Weed cutting in roundhouse and rail storage area.

 
2479 Progress Report - June 16, 2007

Repairs to the Clark forklift have been completed.  The water pump has been rebuilt and installed.  A new seat was acquired, mounting hardware machined and attached.  It has been a number of years since this valuable asset has been fully functional.

The organization's four 35 ton air jacks have been cleaned, lubricated and tested.  These will be used in the near future to lift the locomotive so that the crib supporting the large steel beams which the locomotive rests upon can be replaced.  The present crib is deteriorating.

Cleaning and painting of the locomotive boiler continues.

Documenting the locomotive's jacket is in process.  All of the various jacket pieces have been laid out and measurements taken.  This is the first step in construction of a new jacket.

Weld repairs to the locomotives brake foundation continue.

 
San Jose Steam Railroad Museum Park

On May 6, a 21 page document describing the San Jose Steam Railroad Museum Park was presented to the San Jose City Council.

Click here to view the document (pdf format, 9megabytes).

 
Latest Layout for Coleman Site

From Larry Murchison

ImageClick here to see a revised configuration (pdf format) for the Coleman/Highway 87 site.

You can click on the small aerial photo to get a more detailed image.

A detailed site drawing is also available.

For more photos and models click here to go to the photo gallery.

 
Potential Museum Site Identified

Members of the CTRC leadership have been briefing city agencies and San Jose City Council on conceptual plans for the San Jose Steam Railroad Museum Park.

The location is a vacant privately owned parcel near downtown alongside the Guadalupe River Park trail.  Plans are underway to enlist the fiscal and political support to protect the property and eventually fund the project.  Toward this effort, CTRC has created documents, presentations and a model to share within the community.

 
2479 Progress Report - May 26, 2007

Chamfering of the tell tale holes of the hundreds of new staybolts inside the firebox is nearing completion.  Welding of the final staybolt hole in the firebox has been completed.  Pad welding of the firebox side wrapper sheet has begun with one area completed.

Weld repair of cracks identified in the brake foundation is moving forward.  Cracking of the brake foundation must have been common for 2479.  SP had performed a number of weld repairs to the foundation during its years of service.

Shoe and wedge for driver L2 was test fitted and measurements taken.  Tram wires must now be installed before finally machine work on shoes can take place.  Three of the six journal box to spring saddles have been machined to final length.

Reorganization of various materials at the restoration site continues.  Parts for the lawn tractor have finally been received.  The tractor was assembled this past weekend and returned to service.

 
A Milestone

From John Ezovski

Today the last of the staybolt sleeves were welded to the boiler of 2479.  In a very hot sun, John Blaine completed attaching 3 half sleeves and one full sleeve.

Its been a long road.  There is still so very much remaining.

 
2479 Progress Report - April 28, 2007

From John Esovski

During this past week the crack located at the top of the frame cross member behind number 2 driver was welded.

The shoe and wedge for the fireman's side of number 2 driver were positioned and tested for fit.  Excessive side to side rock was noted for the shoe.  The pedestal face plate was found to have several high spots.  These high spots were removed by light polishing of the surface on Saturday.  The shoe and wedge may now be tested again for fit.

All of the locomotive's driver springs were removed.  The springs have been sitting atop the frame since restoration of the locomotive's equalization system was completed. Removal of the springs was required to allow installation of the journal box saddles at a future date.

Chamfering of staybolts in side the fire box continues.

Gouging out of a crack in the cross member in front of number 1 driver was completed.  This cross member is part of the locomotive's brake foundation.  There are at least three significant cracks in this part.

The lawn tractor is out of service for parts.  Cutting of grass was accomplished with hand pushed power mowers.

 
2479 Progress Report - April 21, 2007

From John Esovski

By far the most significant accomplishment this week was completion of weld repairs to the left pedestal for number 2 driver.  Back in October of 2006, a crack was discovered at the top of the wedge pedestal on the left side of number 2 driver.  A close inspection of all other pedestals  revealed cracks in two other pedestals for number 2 driver.  This past week the third and final crack was welded.

The pedestal crack was discovered during repairs to the four face plates of the number 2 driver pedestals.  Each face plate's attaching welds had cracked nearly all the way around.  During the weld repairs to these plates, the shoe face plate on the left side twisted away from the frame and required a new plate be machined and installed.  This was the second major welding task completed this week.

With the repairs completed to the left side of the frame for number two driver, the shoe and wedge for the left pedestal can be installed and measured to ensure their faces are parallel.  If not, the necessary machining will be completed.  Once this task has been completed, all shoes will be installed and a final tram measurements will be performed.

Also started this week was the chamfering of the telltale holes for all new staybolts.  Chamfering of these holes is necessary to hold a sealing material that blocks soot and other debris from blocking these holes during operation.  During side sheet, throat and combustion chamber repairs, close to 1000 staybolts were replaced.  Each of these bolts must be chamfered.

Started this week was machining of the saddles that interface the locomotive springs to the driver's journal boxes.  This critical step sets the height of the locomotive and more important can determine the weight each journal carries.  Errors here can cause journals to over heat.

Finally comes grass cutting.  The task this week was not as easy as in past weeks.  Our lawn tractor is presently not operational.  Parts  are on back order and may not be available until mid-May.  With site appearance degrading, several workers (J. Zielinski, L. Murchinson, P. Ruhle) broke out the hand push mowers.  They cut a lot of grass during the work day.

Its been a real good week.

Thanks to all!

 
<< Start < Prev 1 2 3 4 5 Next > End >>

Results 49 - 64 of 68

Latest News

It's time for the 27th CTRC Annual Volunteer Recognition BBQ!. Thursday, August 19, 2010 5:00 p.m. to 7:00 p.m. San Jose Historical Museum 1650 Senter Road San Jose, CA Beverages provided by Bottomley Distributing Company BBQ provided by the Santa Clara County Firefighters Local 1165 ...
John Ezovski The Tuesday crew is close to wrapping up the stabilization and cleanup of locomotive SP1215.  The task began in May of last year. I had hoped the job would be complete today, but a hand full of small tasks remain. For those that do not remember what this thing looked, belo...
SP2479 Last component in the locomotive's front coupler pocket has been installed.  With the help of liquid nitrogen, donated by Todd from the Schmahl Science Workshop located at San Jose History Park, the upper hole's bushing was slipped into place on March 29th and the coupler installed....
J Ezovski Despite the many rainy days during the month, there has been progress on both locomotives and improvements at the fairgrounds restoration site. An evaluation of 2479's valve linkage is complete.  Several of the system's bronze bushings must be replaced, several pins require trui...
The trolleys are now operational following an extensive effort to repair damage from a rare lightening strike on January 19th. ...

CTRC Calendar

CTRC meetings are open to members and non-members.  You are welcome even if you are not a member.

We usually have a short (30 minute) discussion of status of the various projects followed by a program.

We meet inside the Santa Clara railroad station itself (you may have to slide one of the sliding doors open to find us.)  In the winter be sure to bring a coat - it can be a bit cool inside the station.

Date: First Monday of each month.

Time: 7pm

Location:
   Santa Clara Railroad Station
   1005 Railroad Avenue
   Santa Clara, California

Click here for map

Upcoming Meetings:

Regular Meetings

  2010
   August 2
   September 6
   October 4
   November 1
   December 6

  2011
   January 3
   Feburary 7
   March 7
   April 4
   May 2
   June 6
   July 4 - no meeting
   August 1
   September 5
   October 3
   November 7
   December 5

Sponsored Links

Submissions

Please send news and other materials by email to karl at cavebear.com.

Syndication

Login Form






Lost Password?