CTRC - The California Trolley and Railroad Corporation. Preserving the historical heritage of railroading and trolleys in the Santa Clara Valley of California.
Ribbon Cutting Ceremony To Be Held On June 3, 2009
City of San Jose, California Trolley and Railroad Corporation and the San Jose Rotary Club Cut Ribbon on Historic Trolley Line!
A new/old trolley line running nearly a mile from the History San Jose Trolley Barn of the California Trolley and Railroad Corporation (CTRC) down Senter Road to Happy Hollow Children’s Park will be inaugurated at 11:00 AM on June 3, next Wednesday at San Jose’s Kelley Park.
This historically significant reestablishment of a trolley service along Senter Road is open to the public and will feature a ribbon-cutting by San Jose Mayor Chuck Reed, City Council members, San Jose Rotary President Bert George and other dignitaries.
This new donor-constructed and volunteer-operated service featuring free rides on the beautifully-restored historic trolley cars will serve the Happy Hollow Park and Zoo, the Leninger Center, the Japanese Friendship Garden, the Rotary Office, and History San Jose.
The free rides will be available to the public after the inauguration ceremony.
For additional media information contact CTRC President Rod Diridon, Sr. at 408 924 7561 or 408 859 4447.
SP1215 Stabilization
The CTRC (Steam team) weekday crew (Larry M, Denis M and John E) has started
the stabilization of SP1215 exterior.
This work was started the week of May 18, 2009.
The plan is to complete stabilization of the side exposed to the HSJ
parking lot first then complete the otherside of the locomotive.
We plan on reinstalling the piping, hand rails, and other items
which were removed when the engine was move to San Jose from Portola California.
In addition the cab will be weather proofed and the rest of the locomotive
will be weatherized.
Before:
After:
SP2479 Status: April to Mid May 2009
April 18
With the move complete and most site infrastructure in place,
work has resumed on the locomotive.
These past two weeks members have been installing the many components that
make up the locomotives braking system.
This may not sound like a significant task, but many of these components
are of significant weight.
Weight combined with working in the now smaller area under the
locomotive's drivers, makes this a sometimes challenging task.
The new site has brought the restoration into a more prominent view
as the locomotive is easily seen from Monterey Highway and Old Tulley Road.
Visitors to the site have been frequent and often surprised about the repairs.
April 25
The fence that will separate the restoration area from the rest of
the fairgrounds is in the process of being installed.
Task should be complete this coming week.
The fence line is between 10 and 20 feet east of our site plan,
thus giving us a bit more space for parking.
Installation of the locomotive brake system continues.
All levers, beams, brake heads and shoes are now installed.
All but three pieces of the brake safety support components are in place.
We were unable to locate two of the remaining three pieces.
One of these pieces may not have been in place when the restoration
effort began.
The missing pieces will be easily formed from 2 1/2" x 1/2" bar stock.
May 9
Removal of the locomotives valves was completed on Saturday.
There were no defects noted to the right side valve and cage assembly.
Things were not so good on the left side.
Several significant gouges were observed in the front valve cage.
One of the three damaged areas is circled in the below image.
More information is needed before repairs can begin.
Initial thoughts are to replace the cage.
While one crew was removing valves, other members worked at recovering
track ballast from the old site.
Mid May
We are starting to have visitors now that the locomotive is visible
from Old Tulley road and, if you look real hard, it can be seen
from Monterey Road.
A lady came to the site with her three little children and we issued
them little hard hats.
They felt like part of the working crew as they were escorted around
the equipment and in the caboose.
The workday crew finished and secured the between-the-container shed.
It now contains the fuel and oil as well as the riding mower and racks
of equipment.
Temporarily the side rods are stored there while bushings are created.
All the equipment from the old location has been moved to our
new location including the turntable and water tank and
a property fence now separates us.
The tender and caboose have been moved up close to the locomotive
so we almost have a "train".
All the under-the-locomotive brake components have been installed.
Two safety bars had to be fabricated.
One other bar needed to be straightened.
It probably was bent in the 1937 wreck and never repaired.
Because of our new, more visible location we now must maintain
the area outside our street-side fenced location.
But the good news is that we no longer need to mow the large acreage
that is now on the other side of the property fence line.
The steam distribution pistons have been removed.
The pistons appear to be OK but one of the internal cages has
a crack that must be evaluated and repaired.
SP2479 Progress: March 23-28, 2009
By John Ezovski
A secure storage area between two containers was completed this past week.
Work included installing gutters along the roof edge, installation of the roof,
attaching chain link fencing along the back, fabrication and installation of
double gates at the entrance.
With the storage area complete, all remaining material was removed from the
women's restroom and deep sink area. The locomotives pistons that were
stored in the men's room entrance area were moved into the outdoor shop
area.
Two and one half panels of track were leveled in preparation of the final move
of the tender and caboose.
While materials were being moved and track leveled, the small shaper/planner
received some much needed attention. Various oil lines were replaced, and
the machine tested.
In addition, grass (weeds) in and adjacent to the new site were cut.
The end of the move is here! By the end of this coming week, all remaining
CTRC equipment (exclusive of the turntable and water tank) should be within
the county designated area.
2479 Update - Feb 28 through March 21 2009
Feb 28
Muddy conditions created by heavy rain during the first part of February slowed
the relocation of CTRC material to the new site but did not stop all work.
Site improvements continued. Fairgrounds staff have spread many more yards of
base rock like material. This has allowed us to ballast and level panels of track
that the locomotive will sit. The dirt bike motorcycle course operator, located
on the fairgrounds, allowed CTRC the use of a loader for several hours this past
week. Ballast from the old site was recovered, spread and tamped under the
panels of track. Some additional ballast is needed between the ties then the
locomotive can be pulled forwarded to the new work area.
The trailer was the last large object to be moved by CTRC members. Several days of work
remain to clear the old site of a number of small items. Dry weather and identifying
a storage location are all that is necessary. On the other hand, much work remains at
the new site.
On Saturday, Feb. 28, the crew decided to take advantage of the prior week's
dry conditions with an
attempt to move organizations 40 by 20 foot double wide trailer.
Tires were installed and the
task of extracting the trailer began.
Eight years ago this trailer was positioned between trees.
(We must have never thought about having to move this trailer again.)
Those trees have grown over
the years combined with the delicate structural integrity of the trailer made
extraction a bit more difficult.
Several hours of jockeying the trailer about were expended.
The trailer was successful rotated into a direction where it
could be pulled across the field to the new location.
The trailer must now be leveled, placed back onto concrete piers and electrical installed.
Mar 7
Today's large crew and dry weather moved several tasks forward. The double wide
trailer received most of the attention. The trailer was placed back on to its concrete
piers and tires were removed.
Thanks to the generosity of Mr. Pedersen of A Tool Shed, a trench was quickly dug from
the main power panel to the trailer. Conduit and wire were laid and electrical power
restored to the trailer.
A second trench was dug from the main power panel over to the rail. A circuit
breaker panel and power outlets, mounted on 4 x 4 posts, was set into the ground.
Conduit and wire have been set into place but several small connection issues remain.
Three months have elapsed since the present phase of site consolidation began. We
are very close to being able to place all of our attention on restoration of SP 2479. All
remaining material should be relocated to the new site in the coming weeks, assuming
relatively dry weather.
Thank you Mr. Pedersen for the use of the walk behind trencher!
Mar 14
Another busy week at the restoration site.
The circuit break and outlet box adjacent to the rail was connected to the
main power source.
Compressed air was also made available at this same location.
The large rack was set into its new location and filled with pallets.
Today a significant amount of material was relocated from the old site and with
this the relocation of CTRC material to the new site is almost complete! One more
day's worth of work is all that is needed to place this task in the complete column.
By the end of the month focus will be back on the locomotive.
Mar 21
Its been another busy week at the restoration site.
The most significant event taking place today. The Saturday crew completed the
necessary track work and pulled the locomotive forward 120 feet to the location
where restoration of SP 2479 may be completed.
The week day crew has begun construction of a storage shed between two of our
containers. This shed will be a secure area for equipment previously stored in rest
rooms at the old location.
This coming week fairgrounds staff will have a crane company provide a quote to
move the turn table and water tank. To help reduce this cost, the week day crew
moved a portion of the structure that supports the large water tank. This large
support is seen in the image below to the right of the double wide trailer.
Today's crew spent most of the day clearing materials from the old site.
Finally, all CTRC materials have been removed from the field previously occupied.
The end of the move is in site!
SP 2479 Update: February. 1 - 7, 2009
This past week a 200 ampere, 3 phase, 220 volt source was connected
at the new site.
The shop was connected to this source and each machine
verified for correct operation.
While machines were being check another
crew was busy plumbing the air compressor.
With all of the electrical issues resolved, the crew turned to repairing
the panels of track that the locomotive will sit for remaining repairs.
Ballast can now be recovered from the old site and the rails leveled.
The rain that has fallen during the past two days has turned the area between
the old and new sites into a large field of mud.
Our Clark forklift is not operable in this environment.
The remaining large objects at the old site,
double wide trailer and large rack, will remain until the ground dries.
Dec. 6, 2008 marked the beginning of this stage in the move.
Much has been accomplished since that date.
In two months crews have relocated three large containers
(and contents), a 26 x 32 foot boiler tube canopy (and all the
equipment it protected), and one 225,000 pound pacific class steam locomotive.
Not bad for two months work!
SP2479 Progress: January 31, 2009
By J. Ezovski
During the week, fairgrounds personnel spread many yards of base rock
and installed posts for the new site's power distribution panel.
Hopefully power will be delivered to the new site early this coming week.
Today's large crew finished turning the locomotive.
The locomotive is now in line with its tender in the new area.
The crew began replacing unserviceable ties in panels that the locomotive
will sit on for future repairs.
Once track repairs are complete, ballast will be spread and the panels leveled.
The locomotive will then be pulled forward about 80 feet to its new location.
With the locomotive close to its new home, the crew turned to relocating the site's
air compressor shed.
This task was completed very late in the afternoon.
Another Thank You to Mr. Pedersen and A Tool Shed.
None of the locomotive moves completed these past three weeks would have been
possible without the help of a second forklift.
The locomotive can almost be pulled by John Blaine's forklift but the
A Tool Shed forklift made the pull easy.
A number of items remain at the old site.
The most significant of these is the double wide trailer.
Moving it will not be easy.
Hopefully it will survive one more move.
Moving the SP2479
By J. Ezovski
With the help of Dennis and Larry Murchison, and Frank Valerga, 2479
began its journey across the fairground to the new site. Four panels of
track were laid out in front of the two panels that the locomotive sat
upon. Near 2 PM, the locomotive was rolled about 170 feet west with the aid
of the Wiggins and A Tool Shed fork lifts.
The above image shows the locomotive coming off of its old location. There was a
slight down grade in this area and the locomotive made good use of it! Air brakes
were rather helpful.
Above shows where the locomotive sat at days end. The front of the locomotive
is very close to the site limit line.
Tomorrow the crew will begin to relocate the panels to the front of the locomotive
for the next step in the move.
SP2479 Progress: January 5-10, 2009
By J. Ezovski
Relocation of our containers is complete. The last container was of
the three units was emptied, moved and equipment returned today,
Saturday, January 10. The task did take most of the day as an unusually
small crew tackled this significant task.
With the container in place, the crew moved over to the locomotive. It was
pulled back to the end of its track, a distance of about fifteen feet. There
were two reasons for this move. First was to see how difficult it was for two
medium size forklifts to move the locomotive. Second reason was to point
the front panel of track in the optimum direction for the coming move.
Surprisingly the locomotive rolled easily. There was virtually no strain placed
on the forklifts.
During the week work continued on the canopy. Rain gutters were reconnected
and a three foot extension was added. Some electrical work was also performed.
Fairgrounds staff continued site work by spreading a layer of base rock.
Another very big thank you to A Tool Shed. Mr. Pedersen's crew delivered a
much needed forklift to the site on Friday. None of the today's work could
have been accomplished without the use of A Tool Shed's lift. None of the
work accomplished over the past month could have been completed with
A Tool Shed's assistance! Thank you Mr. P.!
Fairgrounds management is very satisfied with the move's progress. With some
luck and not a lot of rain, the move could be complete by the end of February.
A number of small items and two big objects remain: locomotive, double wide
trailer.
During the coming week, we hope to have electrical service installed and
power restored to the shop. All parts for the Clark forklift are now at the site.
The lift should be returned to service early in the week. It will then be
placed into service positioning panels of track for the move of the locomotive.
Its been a good week!
Happy Hollow Extension - Construction Begins
Construction has begun on the the Happy Hollow Extension
The crew from Stacy & Witbeck arrived this morning (January 5, 2009) and
started to dig holes for the Happy Hollow Extension poles.
Some of the poles are wood and some are metal in concrete bases.
It may take several weeks for the poles to be installed.
Once installed the installation of the wires can begin.
Come spring the new line will have operating trolleys!
2479 Update - December 2008
The last journal wedge was installed mid November.
It seems that we forgot to trim the wedge to its required thickness before installation.
With boiler finally sitting on its wheels, the steel beam that supported the firebox end of the locomotive was removed.
All cribbing and jacks were removed and stored.
Our focus has now been turned towards relocating to the area designated by the county.
Significant progress had been made during the past several months towards complying with the county's requests.
Earlier all rail material and round house building materials were moved.
The locomotive's tender and caboose were repositioned, but much work remains before we are fully in the new area.
Fairgrounds staff have been most helpful.
Construction of a 36 foot by 28 foot concrete pad has been completed.
This will become our outdoor covered work/machine area.
The immediate area around the pad has been dressed with base rock and leveled.
350 feet of conduit has been laid for electrical power to the shop area.
The past three weekends have been spent repositioning the two 36 foot containers that serve as our
indoor machine shop and finished parts storage.
Both units are now sitting adjacent to the new pad.
Moving these objects have consumed all of our time.
The shop container requiring the most, as it contained two very heavy lathes and Bridgeport mill.
A special event occurred on December 10th. NBC channel 11 visited the site and performed a
live broadcast on CTRC's restoration of SP2479.
Ken Middlebrook was interviewed by Bob Redell for the 11:00 news.
Not all the news has been good.
On December 6th while moving the first container, our large Clark forklift suffered a major casualty.
A shaft between the drive line and the transmission broke. The repair is not difficult, but the part is not readily available.
Efforts to locate the part are on-going.
If a part can not be located, one of our journeymen machinists will be called upon to make one.
Fortunately A Tool Shed has again come to our aid by providing a forklift.
Thank you again A Tool Shed.
J Ezovski
Despite the many rainy days during the month, there has been progress
on both locomotives and improvements at the fairgrounds restoration site.
An evaluation of 2479's valve linkage is complete. Several of the system's
bronze bushings must be replaced, several pins require trui...
On January 19 the area in and around History San Jose
took a number of lightning strikes that include the Power Substation.
PG&E repaired their damage quickly and confirmed that we have 480 VAC to the substation.
After two visits from Cupertino Electric (pro bono), we have identified and re...
J Ezovski
There has been some progress on 2479 the past several months. All components of the
valve gear have been removed from the locomotive and a close inspection of these
components is under way. A bushing was removed from the front coupler. Measurements
indicated that the...
On Monday January 25, 2010, CTRC leadership met with San Jose District 7 Councilwoman Madison Nguyen
to discuss a potential museum location near Kelley Park.
Click here for more information about the museum location.
Situated between two city owned parcels, Municipal Stadium and the main c...
CTRC meetings are open to members and non-members. You are welcome even if you are not a member.
We usually have a short (30 minute) discussion of status of the various projects followed by a program.
We meet inside the Santa Clara railroad station itself (you may have to slide one of the sliding doors open to find us.) In the winter be sure to bring a coat - it can be a bit cool inside the station.
Date: First Monday of each month.
Time: 7pm
Location:
Santa Clara Railroad Station
1005 Railroad Avenue
Santa Clara, California